Green Build Environmental Ltd Complete Remediation Works In Leicester

Green Build Environmental Ltd have successfully completed our remediation package in Leicester. Working as Principal Contractor, we successfully hand picked all Fragmental Asbestos to reduce the volume of Hazardous Muck Away. We then treated and removed 2,800m3 of Hydrocarbon Impacted Soils, as well as an area of Giant Hogweed from around the party wall. We cleared all obstructions down to a two metre depth, re engineered the excavated spoil and constructed a 600mm Pile Mat across the entire site using our 6F5 IBA.