Green Build Environmental Ltd Complete Remediation Works In Leicester
Green Build Environmental Ltd have successfully completed our remediation package in the heart of Leicester.
Working as Principal Contractor, in partnership with the Cost Consultant, our package involved hand picking Fragmental Asbestos to reduce the volume of Hazardous Muck Away that left site, treating and removal of 4,200m3 of Hydrocarbon Impacted Soils, followed by the management and removal of Giant Hogweed from around the party wall.
Finally, we were required to remove all obstructions down to a two metre depth, re engineer the excavated spoil and constructed a 600mm Pile Mat across the entire site using our 6F5 IBA.
The package was completed over a 4-week period.