Case Studies

Green Build Environmental Ltd is proud to be involved with all projects – regardless of size or contract duration.

Below are a few examples of completed projects that enable our clients to understand the types of works that we have been involved with in recent months.

HERTFORDSHIRE

c/o GAVACAN HOMES, Dene Road, Northwood, Middlesex, HA6

Working with our client we successfully removed 11,000m3 of Inert Muck Away from this residential basement excavation for the new build block of luxury apartments. In addition, we supplied 900 tonnes of 6F2 for the piling mat construction and removed a further 1,100m3 of Pile Arisings.

c/o REGAL HOMES, Clarendon Road, Watford, Hertfordshire, WD25

Working with our client we successfully removed 400 tonnes of Hydrocarbon Impacted Soil and a further 600 loads of Inert Muck Away from this residential development. In addition, we also supplied 700 tonnes of Reject Sand and 800 tonnes of Recycled Shingle for the drainage works, as well as 1,000 tonnes of 63/10mm Form Pave, 20/4mm Form Pave and 2/6mm Form Pave for the permeable paving works.

c/o DES, Maple Lodge Close, Rickmansworth, Hertfordshire, WD3

Working with our client we successfully removed 1,900 tonnes of Hazardous Fragmental Asbestos Mixed Muck Away from this commercial development, before undertaking additional sampling, and removing a further 170 loads of Incidental Non Hazardous Muck Away.

c/o INTERSERVE, West Hyde Water Treatment Works, Rickmansworth, Hertfordshire

Working with Interserve we successfully removed 3,000m3 of Hazardous Soil mixed with Asbestos to a facility in Peterborough during phase 1 of the scheme – and an additional 1,500m3 in phase 2. The project started slowly whilst the permit to dig was being processed but after that we removed between 100-200 tonnes per day.

c/o WESTON HOMES, Denham Film Studios, Denham, Hertfordshire

Working with our client we successfully removed 14,000m3 of Non Hazardous Muck Away from this residential development. We also supplied in excess of 700 tonnes of 6F2 for the piling contractor on site.

c/o WILLMOTT DIXON HOMES, Batchwood Garage Sites, St Albans, Hertfordshire

Working with our client we successfully removed over 500 loads of Non Hazardous Muck Away from this residential development. In addition, we also removed 200 tonnes of Hazardous Muck Away and supplied 400 tonnes of Reject Sand for the drainage works.

c/o READIE CONSTRUCTION, East Duck Lees Lane, Brimsdown, Enfield, Hertfordshire

Working with our client we successfully removed 11,000m3 of Inert Muck Away from this project on behalf of Tottenham Hotspur FC. At it’s peak we were removing 700 tonnes per day.

c/o TILBURY DOUGLAS, Watton At Stone Improvement Works, SG14

Working with our client we successfully supplied 16,000 tonnes of a WRAP compliant 6F5 to be used in the permanent works section of this major roadway improvements scheme. At its peak we were supplying 900 tonnes per day.

c/o MULALLEY, Meriden Estate, York Way, Watford, Hertfordshire, WD25

Working with our client we successfully removed 800 tonnes of Hydrocarbon Impacted Hazardous Soil, 8,000m3 of Non Hazardous Muck Away from the reduced dig and supplied over 1,500 tonnes of DOT Type 1 Granite to this residential development. In addition, we sourced and supplied 600 tonnes of Premium Grade Top Soil for use in the back gardens.

c/o WILLMOTT DIXON, Harpenden Leisure Centre Car Park Works, Ammenbury Crescent, Harpenden, Hertfordshire, AL5

Working with our client, and having successfully delivered phase one, we supplied 1,500m3 of Recycled Type 3 and removed 275 loads of Inert Muck Away over a 2 week period, in time for the black topping works that followed in a tight programme. On our follow up visit we removed a further 300 loads of Inert Muck Away and supplied an additional 1,000 tonnes of Recycled Type 3.

c/o HILL PARTNERSHIPS, Crane Mead, Ware, Hertfordshire, SG12

Working with our client we successfully supplied 3,600 tonnes of Recycled 6F2 to construct a piling mat on site at the rate of 600 tonnes per day. We then sampled and removed 8,000m3 of Non Hazardous Muck Away for the basement construction on plots North & South. In addition, we supplied 1,700 tonnes of Type 3 Norwegian Granite for use in the permanent works.

c/o WILLMOTT DIXON, Harpenden Leisure Centre, Ammenbury Crescent, Harpenden, Hertfordshire, AL5

Working with our client we successfully supplied 5,000 tonnes of our Recycled Type 3 Reduced Fines, 3,600 tonnes of Recycled 63-10mm Form Pave, 2,400 tonnes of 10mm Recycled Shingle, 2,000 tonnes of Type 1 Crush and 400 tonnes of Reject Sand.

c/o KIND & CO, 34 Eastbury Avenue, Northwood, Hertfordshire

Working with our client we successfully removed 7,000m3 of Inert Muck Away for the basement construction over a 3 week period.

c/o MULALLEY, Chauncey School, Park Road, Ware, Hertfordshire, SG12

Working with our client we supplied 2,000 tonnes of our Clean Crush No Fines which was used in conjunction with over 300 tonnes of our Recycled 63-10mm Form Pave. We then removed 4,900m3 of Inert Muck Away from the reduced level dig. We also supplied 25 loads of General Purpose Top Soil in grab lorries for the finishing landscape works.

c/o HIGGINS, Alma Road, St Albans, Hertfordshire

Working with our client we successfully removed 3,000m3 Inert Chalk, 4,000m3 Inert Muck Away and a further 1,500 loads Mixed Muck & Tarmac Away from this residential development. Once the units were completed we supplied our 8 wheeler grab lorries to remove the last of the spoil from around the site, as well as supplying 8 yard skips for clay.

c/o BORRAS, Cassiobury Park, Shepherds Road, Gade Avenue, Watford, Hertfordshire

Working with our client we successfully removed the Green Waste from the main parkland itself. We then supplied 600t Type 1 Crushed Concrete, 600t DOT Type 1 Granite and 300t 20mm Recycled Shingle for the drainage. At the back end of the job we removed 40 loads of Re Enforced Concrete from the pools.

c/o HERONSLEA, 106 Camlet Way, Hadley Wood, Hertfordshire

Working with our client we began supplying our Recycled 6F2 for the piling mat construction. When the weather got worse, we switched over to our Clean Crush No Fines material. We then assisted with the pile attendance before removing the bulk dig of 8,000m3. At it’s peak we were removing 45 loads per day.

c/o HERONSLEA, Windmill Street, Bushey, Hertfordshire

Working with our client we undertook the removal of 550 loads of Inert Material Away as well as the supply of quarried Shingle for use within the drainage. In addition, we have supplied over 60 loads of Screened Top Soil to be used in the back gardens.

c/o HERONSLEA, Sparrows Herne, Bushey, Hertfordshire

Working with our client we succesfully undertook the removal of 120 loads per week over a 7 week period of Inert Clay from this new development of flats in Hertfordshire. We also removed the pile caps and the concrete break out whilst the job was in it’s infant stages. Overall we disposed of 9,000m3 of material from site.