Green Build Environmental Ltd is proud to be involved with all projects – regardless of size or contract duration.

Below are a few examples of completed projects that enable our clients to understand the types of works that we have been involved with in recent months.

NORTH LONDON

c/o HILL PARTNERSHIPS, Stonebridge Park, Beames Road, London, NW10

Contract Duration: January 2017 – October 2017

Working with our client we supplied 300 loads of 6F2 for the piling mat and removed an overall 28,000m3 from the basement construction. At the dig’s peak we were removing 1,700 tonnes of Inert Muck Away per day.

c/o GALLIARD HOMES, Islington Square, Almeida Street, Islington, London, N1

Contract Duration: August 2016 – September 2017

Working with our client we undertook additional sampling of the Made Ground to determine the extent of any potential contamination. We then removed 1,400m3 of Concrete Breakout from the obstructions below ground level and then removed 4,000m3 of Piling Mat material before the reduced dig of 42,000m3 of began.

c/o RYDON CONSTRUCTION, Moreton Close, Barnet, London, NW7

Contract Duration: February 2017m – April 2017

Working with our client we successfully removed 200 tonnes of Non Hazardous Muck Away before the 8,000m3 Inert basement dig started. We also supplied 300 tonnes of our 20mm Recycled Shingle for the drainage.

c/o REGAL HOMES, Pentonville Road, Islington, London, N1

Contract Duration: September 2016 – April 2017

Working with our client we successfully removed 800m3 of Non Hazardous spoil and 27,000m3 of Inert Muck Away from this brand new apartment construction. At it’s peak we were removing 1,200t per day. After the bulk dig was completed, we supplied our 8 wheeler grab lorries to remove the remaining spoil from the conveyer belt on a weight and load basis. Our final involvement was the supply of 300 tonnes of DOT Type 1 Granite in bulk bags.

c/o HIGGINS CONSTRUCTION, Coalville Estate, Felton Street, Islington, London, N1

Contract Duration: October 2016 – March 2017

Working with our client we undertook the removal of 11,000m3 of Inert Muck Away from this huge development site in the heart of North London.

c/o MULALLEY, Ashmount School, Ashmount Road, Crouch End, London, N19

Contract Duration: November 2016 – January 2017

Working with our client we successfully removed 400t of Non Hazardous Made Ground followed by 7,000m3 of Inert Muck Away.

c/o HILL PARTNERSHIPS, Agar Place, Off St Pancras Way, Camden, London, NW1

Contract Duration: November 2015 – November 2016

Working with our client we successfully removed 6,000m3 of Inert Muck Away from this new residential development. We also supplied our Recycled 20mm Shingle for the drainage, Type 1 Crushed Concrete for the pathways and Reject Sand for the ducting.

c/o KIND & CO, 30 Muswell Hill, London, N10

Contract Duration: March 2015 – October 2016

Working with our client we were asked to retest the Made Ground to ascertain if the land was contaminated. We then successfully removed 4,700m3 Inert Clay for this basement dig and also provided our brand new 14t Excavators from the very start of the job through H&D Plant Hire. At the back end of the job our fleet of grab lorries removed a further 35 loads of Inert clay.

c/o HIGGINS, Former Blarney Pub, Blackbird Hill, London, NW9

Contract Duration: September 2014 – February 2016

Working with our client we removed over 350 loads of Inert Material and also supplied our 6 Yard Crane Liftable Skips to remove the waste being produced on site. At it’s peak we were carrying out 8-10 exchanges per week as well as supplying Wait & Load bins. Once the job was nearing completion, we removed a further 260m3 of material on grab lorries.

c/o J BREHENY, Summerhouse Lake, Masefield Avenue, Stanmore, Middlesex

Contract Duration: October 2015 – December 2015

Working with our client we removed the top soil stripped material, followed by a further 45 loads Inert Material Away and then we imported over 800t of Recycled Type 1 for use within the compound and permanent works.

c/o WESTON HOMES, Burnt Oak Broadway, Edgware, Middlesex, HA5 8AQ

Contract Duration: November 2014 – November 2015

Working with our client we supplied in excess of 2,400t of Quarried Sharp Sand to be used for screeding at this new accommodation development. Due to the nature of the project and the contracted hours that the screeders were working to we had to supply every load to site before 9am each day.

c/o COUNTRYSIDE PROPERTIES, Grahame Park, Lanacre Avenue, Hendon

Contract Duration: April 2014 – May 2015

Working closely with our client we sampled and then removed the Made Ground to our restorational facility in Essex. We then removed 600-800t per day of Inert Clay to various sites around Hertfordshire. The total volume taken away was 15,000m3 over the course of 4 months. We also supplied our General Purpose Top Soil for the back gardens of the finished residential units and removed the hard standing material to our recycling centre. Phase 2 of the job ran over a 3 weeks period and resulted in us removing an additional 2,700m3 of Inert Muck Away so that the site could be handed over on time.

c/o WATES CONSTRUCTION, Highgate New School, Hampstead Lane, Highgate, N6 4SA

Contract Duration: June 2014 – April 2015

Working with our client we removed 100 loads of crushed demolition material, that was surplus to requirements, prior to carting away 5,000m3 of Inert Muck from the reduced level dig. The site had very strict time restrictions due to the location but this proved to be no issue for us as we had a steady flow of tipper wagons arriving throughout the day. At the back end of the job we supplied our Grab Lorries to remove previously stockpiled material.

c/o ASHE CONSTRUCTION, Stanmore College, Old Church Lane, Stanmore, Middlesex

Contract Duration: December 2013 – July 2014

Working with our client we removed just under 100 loads of Inert Muck Away over a 3 weeks period to enable the site to be clear by Xmas. In addition to this we also supplied 6F2 to build levels on site and to use as a piling mat. In the projects latter stages we supplied a full range of shingles for the drainage contract.

c/o O’HARE & MCGOVERN LTD, West End Lane, Hampstead, NW6

Contract Duration: April 2014 – July 2014

Working with our client we removed up to 500t per day of recyclable material, which had been left from the demolition contractor, to recycling centres in Dunmow & Welwyn Garden City. The material was then used to produce secondary aggregates.

c/o OMEGA, Prince Albert Road, London, NW1

Contract Duration: December 2013 – March 2014

Working with our client we undertook the sampling of soil and then successfully removed 1,400m3 of Muck Away over a 7 week duration. We also supplied 400 tonnes of our DOT Type 1 Crushed Concrete for use within the road construction, and 180t 20mm Recycled Shingle for the drainage.

c/o MCALEER & RUSHE, White Lion Street, Islington, London, N1

Contract Duration: November 2013 – December 2013

Working with our client we removed and recycled 87 loads of made ground as well as undertaking the retesting and removal of the underlying strata for the enabling works package.